Completing or Failing a Task
Completing a task is the normal end to a task. When it is not possible to complete a task normally, due to missing or incomplete data, you can complete a task by failing it, if the appropriate fault response exists.
To complete a task normally:
- On the Task Detail page, supply all output data for all output items, as described in Working with a Work Item, Attachments and Comments.
- If needed, add or remove attachments, and add comments.
- Select Save.
- Select Complete. The task is marked Completed and is no longer displayed in your list of All Open tasks. If desired, you can view a list of All Closed tasks.
To fail a task:
- On the Task Detail page, select Fault from the Output/Fault list, if a fault is available.
- Select the appropriate Fault Name from the list. Note that there may be several faults, one each for a different reason.
- Supply appropriate fault data for the fault, as described in Working with a Work Item, Attachments and Comments. Data is required.
- If needed, add or remove attachments, and add comments.
- Select Save.
- Select Fail. The task is marked Failed and is no longer displayed in your list of All Open tasks. If desired, you can view it in a list of All Closed tasks.
Note: Closed tasks are deleted from your Inbox by an ActiveBPEL Administrator who schedules task deletions.
Go back to About ActiveBPEL Inbox.